Dora Klonari & CO 0,5MW

Solar park with a capacity of 499 kWp. It is located in Agkinara of Pyrgos in the Municipality of Ilia. It started operating in 2012 and produces annually 1520 kWh/kWp.    

Overview

image System name: Dora Klonari& CO
image Operator: Dora Klonari& CO
image Energy company: PPC
image Location: Pyrgos, Municipality of Ilia
image Commissioned: September 2012
image Completion time: 4 weeks

Statistics

0%
Performance Ratio

Technical data

Rated system power:

497,61 kWp

Annual energy yield/kW:

1,52 MWh/kWp

Inverters:

Schneider Electric, GT500E

MV substation:

Schneider Electric

No./type of modules:

1746 units of Suntech, STP285-24/Vd

Construction type:

Ground-mounted

Frame technology:

HILTI

Orientation:

South