Rikia 1MW

Solar park with a capacity of 1000 kW. It is located in Aspropirgos in the Municipality of Attica. It started operating in 2012 and produces annually 1353 kWh/kWp.

Overview

image System name: Rikia
image Operator: -
image Energy company: PPC
image Location: Aspropirgos, Municipality of Attica
image Commissioned: December 2012
image Completion time: 4 weeks

Statistics

0%
Performance Ratio

Technical data

Rated system power:

937 kWp

Annual energy yield/kW:

1,353 MWh

Inverters:

Schneider Conext 20000 TL

MV substation:

Schneider Electric

No./type of modules:

3842 units Canadian Solar, CS6P245

Construction type:

Roof-mounted

Frame technology:

HILTI

Orientation:

East-West